NEW QUESTION 37
How Is the bill of material (BOM) exploded when you use a BOM explosion number?
Please choose the correct answer.
Response:
- A. With respect to a common key date for product and each assembly
- B. With respect to a defined separate change status for product and each assembly
- C. With respect to defined separate key dates for product and each assembly
- D. With respect to a common change status for product and each assembly
Answer: C
NEW QUESTION 38
You are using heuristic SAP_ERP_001. Which of the following criteria are included in the automatic source determination logic when a planned order is created?
Please choose the correct answer.
Response:
- A. Costs
- B. Quota arrangement
- C. Delivery date
- D. Component availability
- E. Vendor rating
Answer: B
NEW QUESTION 39
What does a line hierarchy in repetitive manufacturing represent?
- A. A production line with more than one work center
- B. A production line with prioritized alternative work centers
- C. A production line with an alternative sequence in the routing
- D. A production line with a parallel sequence in the routing
Answer: A
NEW QUESTION 40
When would you use reporting point backflush in repetitive manufacturing?
There are 2 correct answers to this question.
Response:
- A. You require an up-to-date inventory for components
- B. For production lines with short lead times
- C. When goods issues can wait for final confirmation
- D. When you need to determine the work in progress
Answer: C,D
NEW QUESTION 41
An issue storage location was NOT found through the work center, bill of material (BOM)item, or material master. What determines whether the storage location can be derived from the production version?
- A. Plant Data
- B. MRP Controller
- C. MRP Group
- D. MRP Profile
Answer: C
NEW QUESTION 42
You are working with planning strategy 40 (Planning-with-final assembly). When does consumption of planned independent requirements take place?
- A. When the MRP results are saved
- B. When you create a sales order
- C. When you create a planned order
- D. When you deliver a sales order
Answer: B
NEW QUESTION 43
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network? Note: There are
3 correct answers to this question.
- A. SAP Concur
- B. SAP Ariba
- C. SAP C/4HANA
- D. SAP Field glass
- E. SAP SuccessFactors
Answer: A,B,D
NEW QUESTION 44
Which material-specific information can be transferred to a transportation lane in PP/DS?
There are 3 correct answers to this question.
Response:
- A. Production versions
- B. Outline agreement
- C. Purchasing info records
- D. Special procurement keys
- E. Quota arrangements
Answer: B,C,D
NEW QUESTION 45
What data can you maintain in the sub items of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. Quantity
- B. Installation point
- C. Item type
- D. Scrap percentage
Answer: A,B
NEW QUESTION 46
Which of the following is a valid sequence of the main activities in product on order processing?
- A. Creation, staging, release, material withdrawal, confirmation
- B. Creation, scheduling, release, variance calculation, confirmation
- C. Creation, scheduling, release, material withdrawal, confirmation
- D. Creation, release, scheduling, material withdrawal, confirmation
Answer: C
NEW QUESTION 47
The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?
- A. Use the minimum order quantity.
- B. Use the MRP type for vendor managed inventory.
- C. Use the fixed lot size procedure.
- D. Use the reorder point.
Answer: C
NEW QUESTION 48
Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What is the impact of this decision? Note: There are 3 correct answers to this question.
- A. Sales order-specific planning run is required.
- B. Sales order-specific stock is created
- C. Production orders are created with sales order reference.
- D. Storage location MRP areas are required.
- E. Net requirements calculation is sales order-specific.
Answer: B,C,E
NEW QUESTION 49
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Work Center BOM
- B. Sales Order BOM
- C. Functional Location BOM
- D. Class BOM
Answer: B,C
NEW QUESTION 50
When can the material availability check occur automatically in a production order? Note: There are 2 correct answers to this question.
- A. At order release
- B. At order confirmation
- C. At order creation
- D. At order settlement
Answer: A,C
NEW QUESTION 51
You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?
- A. Squeezing
- B. Find Slot
- C. Scheduling working time only
- D. Insert operation
Answer: B
NEW QUESTION 52
How can you set up the supply source for the SAP Kanban process? Note: There are 3 correct answers to this question.
- A. Using quotations for internal and external procurement
- B. Using purchase orders for external procurement
- C. Using run schedule quantities for in-house production
- D. Using stock transfer reservations for stock transfer
- E. Using purchasing costs for automated source prioritization
Answer: B,C,D
NEW QUESTION 53
Which Kanban master data object controls the relationship between the supply and demand source?
Please choose the correct answer.
Response:
- A. Control cycle
- B. Kanban container
- C. Production supply area
- D. Rate routing
Answer: A
NEW QUESTION 54
......