PASS C-TS412-2021 exam with SAP Real Exam Questions - 100% Valid! Actual C-TS412-2021 Exam Recently Updated Questions with Free Demo SAP C_TS412_2021 certification exam is a comprehensive test that covers a variety of topics related to SAP S/4HANA Project Systems. These topics include project planning, project execution, project monitoring and controlling, and project closing. C-TS412-2021 exam also [...]

[Q34-Q57] PASS C-TS412-2021 exam with SAP Real Exam Questions - 100% Valid!

Share

PASS C-TS412-2021 exam with SAP Real Exam Questions - 100% Valid!

Actual C-TS412-2021 Exam Recently Updated Questions with Free Demo


SAP C_TS412_2021 certification exam is a comprehensive test that covers a variety of topics related to SAP S/4HANA Project Systems. These topics include project planning, project execution, project monitoring and controlling, and project closing. C-TS412-2021 exam also covers project structures, cost planning, revenue planning, and resource planning.

 

NEW QUESTION # 34
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question

  • A. A bill of material with sales views
  • B. Standard network with activities
  • C. A material master with sales views
  • D. Assignment between material and standard network
  • E. A production order

Answer: B,C,D


NEW QUESTION # 35
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.

  • A. Usage of cost elements is mandatory
  • B. Sales prices are maintained in the DIP profile
  • C. DIP is used to create a quotation
  • D. Sources can be based on line items
  • E. Material determination is mandatory

Answer: B,D,E

Explanation:
Dynamic item processor (DIP) is a tool that allows you to create sales order items automatically based on project data. Some of the features of DIP are: Sales prices are maintained in the DIP profile, which is a parameter that defines how sales order items are created and priced from project data. Sources can be based on line items, which means that you can use individual cost elements or revenue elements as sources for creating sales order items. Material determination is mandatory, which means that you have to assign a material number to each source in order to create sales order items. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 36
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.

  • A. Vendor selection- Purchase order handing-purchase order monitoring-Good receipt- Invoice receipt.
  • B. Benefic check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoce ..
  • C. Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt.
  • D. Vendor selection - purchase order handing- purchase order monitoring- Benefic Check- Acceptance of performed services.

Answer: A

Explanation:
"The typical sequence for the following business transactions and documents is: Vendor selection - Purchase order handling - Purchase order monitoring - Goods receipt - Invoice receipt." Reference: 1


NEW QUESTION # 37
Which object is relevant in assembly processing to create an assembly order for the SD document?

  • A. Project profile
  • B. Control key
  • C. Item category
  • D. Requirement class

Answer: A


NEW QUESTION # 38
Which report can use user-specific layouts?

  • A. Enhanced individual overview
  • B. Cost element report
  • C. Hierarchical report
  • D. Line item report

Answer: D

Explanation:
A line item report is a report type that can use user-specific layouts. A line item report displays detailed information on individual cost or revenue elements for project objects, such as WBS elements or activities. You can use user-specific layouts to define which fields are displayed or hidden, how they are sorted or filtered, and how they are totaled or subtotaled. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 39
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

  • A. Network profile
  • B. Project profile
  • C. Data entry profile
  • D. Network type

Answer: B


NEW QUESTION # 40
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

  • A. The exact lot size procedure must be used
  • B. The procurement type of the material must be internal
  • C. The materials must allow sales order or project stock
  • D. An MRP group must be assigned

Answer: C,D

Explanation:
Requirements grouping of materials is a process that allows you to plan and procure materials jointly for several WBS elements within a project or across projects. To use requirements grouping of materials, the materials must allow sales order or project stock, which means they must have a special procurement type of E or Q in the material master. An MRP group must also be assigned to the materials, which defines the parameters for material requirements planning, such as lot size and planning strategy. Reference: https://help.sap.com/doc/78f5c353b677b44ce10000000a174cb4/700_SFIN20%20006/en-US/0814c353b677b44ce10000000a174cb4.html


NEW QUESTION # 41
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?

  • A. Set up the requirement date aligned with the activity start date and an offset of 5 days.
  • B. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
  • C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
  • D. Set up the requirement date manually as February 5.

Answer: A


NEW QUESTION # 42
Which organizational structures are required for network activities? Note: There are 3 correct answers to this question

  • A. Plant
  • B. Operating concern
  • C. Sales organization
  • D. Controlling area
  • E. Company code

Answer: A,D,E

Explanation:
Controlling area, plant, and company code are some of the organizational structures required for network activities. Controlling area is an organizational unit that represents a closed system for cost accounting purposes. Plant is an organizational unit that represents a location where materials are produced or services are provided. Company code is an organizational unit that represents an independent accounting entity with its own balance sheet and profit and loss statement. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 43
You are working with networks and WBS elements. Which of the following statements applies?

  • A. You can reassign an activity from one network to another.
  • B. You have to activate the operative indicator Account Assignment Element for WBS elements with activities.
  • C. You have to maintain a network profile in the project profile.
  • D. You can assign the network header to multiple WBS elements.

Answer: A,D


NEW QUESTION # 44
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

  • A. In the WBS element
  • B. In the material master
  • C. In the project definition
  • D. In the network activity

Answer: B

Explanation:
To control whether a project stock is managed as valuated or non-valuated project stock, you have to maintain the setting in the material master. The material master is a set of data that defines the characteristics and properties of a material that can be produced or procured. The material master contains various views that store different types of information about a material, such as basic data, sales data, purchasing data, accounting data, and so on. In the accounting view of the material master, you can specify whether a material is relevant for valuated project stock or not by using the Valuation category field. The valuation category is a parameter that determines how a material is valuated in different stock accounts. If you select Q as the valuation category for a material, it means that the material is relevant for valuated project stock and its value is updated in Financial Accounting. If you leave the valuation category blank for a material, it means that the material is relevant for non-valuated project stock and its value is not updated in Financial Accounting. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 45
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question

  • A. Saving a goods receipt
  • B. Saving a service entry shee
  • C. Saving a purchase order
  • D. Saving a supplier invoice

Answer: B,D

Explanation:
Saving a supplier invoice and saving a service entry sheet are some of the actions that can transfer actual costs for external processing. External processing is a process that involves procuring services from external vendors for project activities. Saving a supplier invoice is an action that records the payment request from a vendor for the services performed and posts actual costs to the project. Saving a service entry sheet is an action that records the delivery of services from a vendor and posts actual costs to the project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 46
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.

  • A. A network can be activity-account-assigned and header-account-assigned.
  • B. A network activity can be assigned to several WBS elements.
  • C. Relationships can be used to connect activities of different networks.
  • D. Material components can be assigned to activity elements.

Answer: A,C


NEW QUESTION # 47
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.

  • A. Standard Project definition
  • B. Project definition
  • C. Project milestone
  • D. Project version.
  • E. Standard network

Answer: A,B,E

Explanation:
A template is a predefined structure that can be used to create a new project with network in the Project Builder (CJ20N). You can use different types of templates depending on your requirements and preferences. Some of these templates are:
Standard network: This is a template that contains predefined activities, relationships, milestones, and components for a network. You can use a standard network to create a new network with similar structure and content.
Standard Project definition: This is a template that contains predefined WBS elements, networks, activities, relationships, milestones, and components for a project. You can use a standard project definition to create a new project with similar structure and content.
Project definition: This is an existing project that can be used as a template for creating a new project with network. You can use a project definition to copy the entire structure and content of an existing project or only selected parts of it. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002


NEW QUESTION # 48
Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question

  • A. Project-relevant purchase orders
  • B. Production orders assigned to WBS elements
  • C. Maintenance orders assigned to an activity
  • D. Capacity requirements

Answer: C,D

Explanation:
The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other objects such as WBS elements, networks, activities, milestones, production orders, sales orders, purchase orders, and so on. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002


NEW QUESTION # 49
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct answers to this question.

  • A. Reservations
  • B. Purchase order items
  • C. Sales order items
  • D. Internal orders

Answer: A,B

Explanation:
Project-Oriented Procurement (ProMan) is a tool that allows you to display and process procurement documents that are relevant for projects. You can use ProMan to display reservations and purchase order items that are assigned to WBS elements or network activities. You can also use ProMan to create purchase requisitions, purchase orders, goods movements, and invoices for project-related materials and services. Reference: https://help.sap.com/saphelp_erp60_sp/helpdata/EN/8e/8bc95360267214e10000000a174cb4/frameset.htm


NEW QUESTION # 50
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

  • A. The Project Stock indicator is set in the project definition (non-valuated or valuated)
  • B. A procurement indicator must be assigned to the activity
  • C. The material master of the component must permit project stock management
  • D. The network activity is assigned to a WBS element
  • E. The network is assigned to a sales order item

Answer: A,C,D

Explanation:
To generate project stock reservations for a component assigned to a network activity, the following prerequisites must be met:
The network activity must be assigned to a WBS element that is relevant for project stock management.
The material master of the component must have a procurement type that allows project stock management (such as E, F, or X) and an individual/collective requirements indicator that allows individual requirements (such as 2 or 4).
The project definition must have the Project Stock indicator set to either non-valuated or valuated project stock. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002


NEW QUESTION # 51
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

  • A. The factory calendar in the work center used for the internal processing activity
  • B. An activated Scheduling indicator in the control key of the internal processing activity
  • C. Whether the work for the internal activity is greater than its duration
  • D. The unit (for example, hour, day) of the field Normal Duration field of the activity
  • E. The relationships between activity elements

Answer: A,B,D


NEW QUESTION # 52
Resources
Which of the following transactions can you use to post actual cost for external processing.
Note : there are 2 correct answer for this question.

  • A. Creating a service entry sheet
  • B. Approval of a good receipt.
  • C. Creating a purchase order.
  • D. Approval of a service entry sheet
  • E. Posting a goods receipt

Answer: B,D

Explanation:
The approval of a service entry sheet and the approval of a goods receipt are both transactions that can be used to post actual costs for external processing." Reference: 3


NEW QUESTION # 53
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question

  • A. Goods receipt into unvaluated project stock
  • B. Goods receipt of a non-stock item
  • C. Recording of external services in the service entry sheet
  • D. Goods receipt into valuated project stock

Answer: A,B

Explanation:
Goods receipt into unvaluated project stock and goods receipt of a non-stock item do not lead to the booking of actual costs to an object. Goods receipt into unvaluated project stock does not affect inventory valuation or accounting documents, therefore no actual costs are posted. Goods receipt of a non-stock item does not affect inventory valuation either, but only updates the purchase order history and statistical delivery costs, therefore no actual costs are posted. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 54
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

  • A. Project profile
  • B. Network profile
  • C. Data entry profile
  • D. Network type

Answer: C


NEW QUESTION # 55
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.

  • A. Allow business processes forbidden by SAP system status
  • B. Restrict setting user status for individual users
  • C. Ensure user status must always be set manually
  • D. Utilize priorities for setting the user status

Answer: B,C


NEW QUESTION # 56
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.

  • A. Use an offset of two days for milestone date.
  • B. Use an offset of two days for the relationship of both activities.
  • C. Use an offset of two days for the requirement date of the material component
  • D. Calculate the start date of the activity and set the constraint "Must start on" accordingly.

Answer: B,D

Explanation:
"You can use an offset to specify a time interval between two activities. For example, you can specify that an activity should start two days after its predecessor activity has finished." According to SAP Help Portal2, "You can use constraints to specify fixed dates for activities. For example, you can use the constraint 'Must start on' to fix the start date of an activity." Reference: 12


NEW QUESTION # 57
......


SAP C-TS412-2021 Certification Exam is designed for professionals who want to demonstrate their knowledge and skill in SAP S/4HANA Project Systems. SAP Certified Application Associate - SAP S/4HANA Project Systems certification is a validation of the candidate's ability to configure, implement, and customize the SAP S/4HANA Project Systems module. It also proves their expertise in managing and executing projects using SAP S/4HANA Project Systems.

 