This Web Simulator is your complete solution for CompTIA Project+ exam preparation. Covering 100% of PK0-004!! The Web Simulator gives you everything you need to ensure that you not only understand the basics of project management, so you can demonstrate your understanding effectively how to run small and big projects.
The Web Simulator provides the best practice questions for CompTIA PK0-004 Exam for your ultimate success in first attempt. We will provide you 100% updated and exam Preparation material that cover all the topics in the PK0-004 exam. The Web Simulator is designed for CompTIA Project+ is designed for business professionals who coordinate or manage small-to-medium-size projects, inside and outside of IT. The practice tests for PK0-004 exam certifies the knowledge and skills required to manage the project life cycle, ensure appropriate, communication, manage resources, manage stakeholders, and maintain project documentation.
NEW QUESTION 66
A team member has reported Task 3 will be completed ahead of schedule.
Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?
- A. 10 days
- B. 12 days
- C. 11 days
- D. 8 days
Answer: B
NEW QUESTION 67
Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days. Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A. Tasks D and E start after Task C. Which of the following is the critical path if Task B starts on Day 3?
- A. A, D, E
- B. B, C, E
- C. A, C, E
- D. A, C, D
Answer: C
NEW QUESTION 68
Rather than sending emails to communicate all project information, the project manager:
* Makes telephone calls to key stakeholders for urgent information
* Sends emails for routine information
* Posts on the project intranet site for required but minimally used information Which of the following BEST represents what the project manager is doing?
- A. Adjusting the method based on confidentiality constraints
- B. Tailoring the method based on message content
- C. Demonstrating concern for technological factors
- D. Prioritizing based on personal preferences
Answer: B
NEW QUESTION 69
Which of the following risk strategies prevents a risk from impacting a project?
- A. Transfer risk
- B. Mitigate risk
- C. Accept risk
- D. Avoid risk
Answer: D
Explanation:
Reference:
https://pm4id.org/chapter/11-2-risk-management-process/
NEW QUESTION 70
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation?
(Choose two.)
- A. A change management plan to have the vendor replaced.
- B. The scope statement to show why the vendor should be replaced.
- C. A procurement plan to show why the vendor should be replaced.
- D. The team action items to show why the vendor should be replaced.
- E. The issue log to show why the vendor should be replaced.
Answer: A,E
Explanation:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.
291, p. 327
NEW QUESTION 71
A project team is showing off a new product prototype at a trade show, and potential customers are requesting more information.
Which of the following is the MOST efficient way to provide more information?
- A. Printed media
- B. Email
- C. Video conference
- D. Meeting
Answer: A
NEW QUESTION 72
Team members have reported poor sound quality during critical, time-sensitive conference calls. Which of the following may be a more effective means of communication?
- A. Text messages
- B. Social media
- C. One-on-one meetings
- D. Project wiki
Answer: C
NEW QUESTION 73
A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved.
Which of the following constraints are MOST likely to be affected? (Choose two.)
- A. Quality because the existing system is now outside the threshold.
- B. Schedule because this was an unscheduled task and will impact the timeline.
- C. Requirements because this is a change to initial scope.
- D. Cost because replacing the system incurs additional expense.
- E. Stakeholders because they will need to understand the modification and provide buy-in.
Answer: B,D
Explanation:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293
NEW QUESTION 74
A project manager has identified a minor skills gap in the operational team that will end up supporting the project solution.
Which of the following is the BEST risk mitigation strategy that the project manager should use?
- A. Raise a risk in the risk register, identify the likelihood and the consequence of the risk occurring.
- B. Have the project adequately document the solution and ensure a transition is in place.
- C. Organize adequate training and have one of the operational staff as part of the project team.
- D. Escalate this as an issue to the project control board and ensure that there is adequate discussion.
Answer: C
NEW QUESTION 75
Which of the following is a definition of an RFP?
- A. A document sent to potential vendors to request information for skills and experience for a project
- B. A document sent to potential vendors to solicit a bid for a project
- C. A document sent to potential vendors to request a commitment for a project
- D. A document sent to potential vendors to solicit information that excludes pricing information for a project
Answer: D
NEW QUESTION 76
A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility.
Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?
- A. Email
- B. Social media
- C. Text messaging
- D. Face-to-face
Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
NEW QUESTION 77
Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?
- A. Critical Path Method
- B. Gantt Chart Method
- C. Arrow Diagramming Method
- D. Critical Chain Method
Answer: C
Explanation:
Explanation/Reference:
NEW QUESTION 78
A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?
- A. Issue log
- B. Dashboard information
- C. Action items
- D. Communication plan
Answer: A
NEW QUESTION 79
Which of the following is a team-building stage that involves the team learning to trust one another's abilities and begin working together as a productive group?
- A. Storming
- B. Performing
- C. Forming
- D. Norming
Answer: D
Explanation:
Norming is where things begin to calm down. Team members know each other fairly well by now.
They're comfortable with their positions in the team, and they begin to deal with project problems instead of people problems. "Decisions are made jointly at this stage, and team members "exhibit mutual respect and familiarity with one another.
NEW QUESTION 80
Which of the following risk strategies is represented by the purchase of insurance?
- A. Accept
- B. Mitigate
- C. Transfer
- D. Avoid
Answer: C
Explanation:
Explanation
"Transfer: Moving the liability for the risk to a third party by purchasing insurance, performance bonds, and so on"
NEW QUESTION 81
Which of the following is a component of the project cost control?
- A. Burn rate
- B. MOU
- C. SLA
- D. Scope statement
Answer: D
NEW QUESTION 82
In which of the following categories does a business process change fit?
- A. Organizational change
- B. Project change
- C. Departmental change
- D. General change
Answer: A
Explanation:
Explanation
Explanation
"Business process changes typically occur within the organization. An example of a business process change is automating a process that previously was performed on paper. If your project has anything to do with this process or is impacted by the process, changes will be coming your way" Excerpt From: Kim Heldman. "CompTIA Project+ Study Guide." iBooks.
NEW QUESTION 83
Language barriers will MOST likely influence a PM to:
- A. use more print media to communicate with the stakeholders.
- B. hire a bilingual project team that is fluent in the language to reduce conflict.
- C. learn the unknown language to be able to communicate effectively with stakeholders.
Section: (none)
Explanation - D. hire an interpreter to ensure verbal and written communications are accurate.
Answer: B
NEW QUESTION 84
A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?
- A. Balanced scorecard
- B. SWOT matrix
- C. Process diagram
- D. Change control plan
Answer: D
NEW QUESTION 85
......
CompTIA PK0-004 is a required exam for earning the CompTIA Project+ certification. The test is designed to equip the candidates with the skills needed to manage a project’s lifecycle, manage the stakeholders and resources, ensure clear communications, and keep project documentation. Those specialists who pass this exam will be able to understand the basic concepts required to manage small- to medium-sized projects successfully.
Our PK0-004 dumps will include those topics:
- Project Tools and Documentation 21%
- Communication and Change Management 26%
- Project Constraints 17%
- Project Basics 36%
For more info visit: CompTIA Project+